Dept. of Trans. PROGRESS Serial No. Contract No. 09-356-09-28 05-0A4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 82% 05-SLO-227-R10.9/R14.2 Federal Project: ACNH-S227(5) Progress payment No. 16 Payment period ending: 12-20-09 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,706,533.03 732,921.50 2.a. Extra Work 217,607.05 22,747.87 b. Adjustment Comp. -258,363.47 0.00 3. Materials on Hand 0.00 -7,249.46 4. Earned Subject to Retention 6,665,776.61 748,419.91 5. Mobilization 157,000.00 0.00 6. Total Work Completed 6,822,776.61 7. Deductions -69,283.47 -66,629.72 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,753,493.14 681,790.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 681,790.19