Dept. of Trans. PROGRESS Serial No. Contract No. 10-025-12-57 05-0A4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 85% 05-SLO-227-R10.9/R14.2 Federal Project: ACNH-S227(5) Progress payment No. 17 Payment period ending: 01-20-10 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,291,963.38 585,430.35 2.a. Extra Work 289,419.96 71,812.91 b. Adjustment Comp. -340,198.11 -81,834.64 3. Materials on Hand 4. Earned Subject to Retention 7,241,185.23 575,408.62 5. Mobilization 157,000.00 0.00 6. Total Work Completed 7,398,185.23 7. Deductions -12,653.75 56,629.72 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,385,531.48 632,038.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 632,038.34