Dept. of Trans. PROGRESS Serial No. Contract No. 10-083-10-45 05-0A4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 92% 05-SLO-227-R10.9/R14.2 Federal Project: ACNH-S227(5) Progress payment No. 19 Payment period ending: 03-20-10 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,285,413.57 13,430.41 2.a. Extra Work 357,109.36 18,949.83 b. Adjustment Comp. -340,198.11 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,302,324.82 32,380.24 5. Mobilization 157,000.00 0.00 6. Total Work Completed 7,459,324.82 7. Deductions -2,725.00 -14.25 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,456,599.82 32,365.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,365.99