Dept. of Trans. PROGRESS Serial No. Contract No. 10-111-15-25 05-0A4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 95% 05-SLO-227-R10.9/R14.2 Federal Project: ACNH-S227(5) Progress payment No. 20 Payment period ending: 04-20-10 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,300,685.06 15,271.49 2.a. Extra Work 443,328.30 86,218.94 b. Adjustment Comp. -373,585.22 -33,387.11 3. Materials on Hand 4. Earned Subject to Retention 7,370,428.14 68,103.32 5. Mobilization 157,000.00 0.00 6. Total Work Completed 7,527,428.14 7. Deductions -2,725.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,524,703.14 68,103.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 68,103.32