Dept. of Trans. PROGRESS Serial No. Contract No. 10-145-14-59 05-0A4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 97% 05-SLO-227-R10.9/R14.2 Federal Project: ACNH-S227(5) Progress payment No. 21 Payment period ending: 05-20-10 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,316,185.06 15,500.00 2.a. Extra Work 556,854.92 113,526.62 b. Adjustment Comp. -364,567.88 9,017.34 3. Materials on Hand 4. Earned Subject to Retention 7,508,472.10 138,043.96 5. Mobilization 157,000.00 0.00 6. Total Work Completed 7,665,472.10 7. Deductions -2,725.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,662,747.10 138,043.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 138,043.96