Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-167-12-42 05-0A4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SLO-227-R10.9/R14.2 Federal Project: ACNH-S227(5) Progress payment No. 22 Payment period ending: 05-27-10 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,317,410.06 1,225.00 2.a. Extra Work 588,230.40 31,375.48 b. Adjustment Comp. -364,567.88 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,541,072.58 32,600.48 5. Mobilization 157,000.00 0.00 6. Total Work Completed 7,698,072.58 7. Deductions -15,000.00 -12,275.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,683,072.58 20,325.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,325.48