Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-179-11-40 05-0A4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SLO-227-R10.9/R14.2 Federal Project: ACNH-S227(5) Progress payment No. 23 Payment period ending: 05-27-10 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,317,410.06 0.00 2.a. Extra Work 595,318.94 7,088.54 b. Adjustment Comp. -364,567.88 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,548,161.12 7,088.54 5. Mobilization 157,000.00 0.00 6. Total Work Completed 7,705,161.12 7. Deductions -15,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,690,161.12 7,088.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,088.54