Dept. of Trans. PROGRESS Serial No. Contract No. 06-024-08-47 05-0C1004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SLO-101-12.5/14.7 Federal Project: ACNH-Q101(31) Progress payment No. 19 Payment period ending: 01-20-06 J S BRAR COMPANY 2779 BULLARD AVENUE CLOVIS CA 936113414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,125,211.45 5,475.75 2.a. Extra Work 24,295.24 0.00 b. Adjustment Comp. -3,500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,146,006.69 5,475.75 5. Mobilization 51,300.00 0.00 6. Total Work Completed 1,197,306.69 7. Deductions -26,804.91 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,170,501.78 4,475.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,475.75