Dept. of Trans. PROGRESS Serial No. Contract No. 15-323-15-01 05-0C6404 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 15% Location: Federal Project: 05-SB-246-12.3/R16.7 NONE Progress payment No. 007 Payment period ending: 11-20-15 PAPICH CONSTRUCTION CO. INC. PO BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 447,430.03 95,442.73 2. a. Extra Work 41,835.51 11,862.92 b. Adustment Comp. 3. Materials on Hand 85,542.03 -747.36 4. Earned Subject to Retention 574,807.57 106,558.29 5. Mobilization 6. Total Work Completed 489,265.54 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 574,807.57 106,558.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 106,558.29