Dept. of Trans. PROGRESS Serial No. Contract No. 18-023-09-11 05-0C6404 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 90% Location: Federal Project: 05-SB-246-12.3/R16.7 NONE Progress payment No. 031 Payment period ending: 01-20-18 PAPICH CONSTRUCTION COMPANY INC PO BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,883,256.41 635,606.68 2. a. Extra Work 2,533,001.66 0.00 b. Adustment Comp. -60,279.48 0.00 3. Materials on Hand 14,724.08 -11,742.76 4. Earned Subject to Retention 14,370,702.67 623,863.92 5. Mobilization 388,340.95 0.00 6. Total Work Completed 14,744,319.54 7. Deductions -4,260.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,754,783.62 623,863.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 623,863.92