Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 08-191-12-51 05-0C6604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 71% 05-SLO-166-9.5/10.1 Federal Project: 05-SLO-166-13.2/13.7 STP Progress payment No. 04 Payment period ending: 06-20-08 SOUZA CONSTRUCTION INC P O BOX 3810 SAN LUIS OBISPO CA 934033810 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 505,202.65 208.75 2.a. Extra Work 6,137.57 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 511,340.22 208.75 5. Mobilization 33,060.00 0.00 6. Total Work Completed 544,400.22 7. Deductions 8. a.Contract Retentions -25,769.62 0.00 b. Unsatisfactory Prog. 0.00 15,154.66 c. Reduction after 95% Comp. 9. Total pay to Contractor 518,630.60 15,363.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,363.41