Dept. of Trans. PROGRESS Serial No. Contract No. 24-023-20-28 05-0C7324 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 14% Location: Federal Project: 05-SCR-1-13.6/14.9 ACNH-P001(675) Progress payment No. 012 Payment period ending: 01-20-23 GRANITE CONSTRUCTION COMPANY 580 WEST BEACH ST WATSONVILLE CA 95076 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,093,718.74 487,149.72 2. a. Extra Work 24,160.43 15,742.93 b. Adustment Comp. 14,267.50 0.00 3. Materials on Hand 183,896.00 0.00 4. Earned Subject to Retention 9,316,042.67 502,892.65 5. Mobilization 2,660,000.00 0.00 6. Total Work Completed 11,792,146.67 7. Deductions -65,000.00 -40,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,911,042.67 462,892.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 462,892.65