Dept. of Trans. PROGRESS Serial No. Contract No. 25-323-19-11 05-0C7324 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 38% Location: Federal Project: 05-SCR-1-13.6/14.9 ACNH-P001(675) Progress payment No. 041 Payment period ending: 11-20-25 GRANITE CONSTRUCTION COMPANY 580 WEST BEACH ST WATSONVILLE CA 95076 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,352,060.50 -631,479.75 2. a. Extra Work 5,623,954.70 641,729.00 b. Adustment Comp. -104,245.92 0.00 3. Materials on Hand 4. Earned Subject to Retention 30,871,769.28 10,249.25 5. Mobilization 2,800,000.00 0.00 6. Total Work Completed 33,671,769.28 7. Deductions -202,331.25 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 33,469,438.03 10,249.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,249.25