Dept. of Trans. PROGRESS Serial No. Contract No. 25-084-10-18 05-0C7334 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 17% Location: Federal Project: 05-SCR-1-10.5/13.4 NONE Progress payment No. 018 Payment period ending: 03-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,044,770.82 149,968.86 2. a. Extra Work 644,386.20 98,496.81 b. Adustment Comp. 3. Materials on Hand 146,923.64 -4,469.00 4. Earned Subject to Retention 21,836,080.66 243,996.67 5. Mobilization 6,840,000.00 0.00 6. Total Work Completed 28,529,157.02 7. Deductions -103,594.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,572,486.66 233,996.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 233,996.67