Dept. of Trans. PROGRESS Serial No. Contract No. 25-157-09-52 05-0C7334 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 22% Location: Federal Project: 05-SCR-1-10.5/13.4 NONE Progress payment No. 022 Payment period ending: 06-05-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,753,070.00 0.00 2. a. Extra Work 969,312.45 70,551.24 b. Adustment Comp. 195,227.24 195,227.24 3. Materials on Hand 340,894.14 0.00 4. Earned Subject to Retention 25,258,503.83 265,778.48 5. Mobilization 6,840,000.00 0.00 6. Total Work Completed 31,757,609.69 7. Deductions -118,594.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,979,909.83 265,778.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 265,778.48