Dept. of Trans. PROGRESS Serial No. Contract No. 26-082-07-59 05-0C7334 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 23% Location: Federal Project: 05-SCR-1-10.5/13.4 NONE Progress payment No. 036 Payment period ending: 03-20-26 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 39,101,322.15 1,021,794.98 2. a. Extra Work 2,719,899.52 -7,735.92 b. Adustment Comp. 275,679.56 0.00 3. Materials on Hand 280,195.04 0.00 4. Earned Subject to Retention 42,377,096.27 1,014,059.06 5. Mobilization 7,200,000.00 0.00 6. Total Work Completed 49,296,901.23 7. Deductions -372,108.77 -238,514.77 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 49,204,987.50 775,544.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 775,544.29