Dept. of Trans. PROGRESS Serial No. Contract No. 06-298-13-40 05-0C8704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 94% 05-SLO-101-58.3/ .0 Federal Project: 05-SLO-1-45.6/ .0 NONE 05-SLO-101-26.3/ .0 Progress payment No. 05 Payment period ending: 10-20-06 CLAYBORN CONTRACTING GROUP INC 10556 COMBIE ROAD AUBURN CA 956028908 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 560,591.00 71,617.90 2.a. Extra Work b. Adjustment Comp. -13,769.22 -10,871.22 3. Materials on Hand 4. Earned Subject to Retention 546,821.78 60,746.68 5. Mobilization 6. Total Work Completed 546,821.78 7. Deductions 8. a.Contract Retentions -27,341.09 -3,037.33 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 519,480.69 57,709.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,709.35