Dept. of Trans. PROGRESS Serial No. Contract No. 07-206-08-02 05-0C8704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SLO-101-58.3/ .0 Federal Project: 05-SLO-1-45.6/ .0 NONE 05-SLO-101-26.3/ .0 Progress payment No. 14 Payment period ending: 07-20-07 CLAYBORN CONTRACTING GROUP INC 10556 COMBIE ROAD AUBURN CA 956028908 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 592,459.12 971.52 2.a. Extra Work 6,328.50 0.00 b. Adjustment Comp. -13,769.22 0.00 3. Materials on Hand 4. Earned Subject to Retention 585,018.40 971.52 5. Mobilization 6. Total Work Completed 585,018.40 7. Deductions 8. a.Contract Retentions -29,250.92 -48.58 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 555,767.48 922.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 922.94