Dept. of Trans. PROGRESS Serial No. Contract No. 09-294-13-21 05-0C9024 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 75% 05-SCR-1-8.0/17.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-20-09 NORWOOD CONSTRUCTION 5301 BYRON HOT SPRINGS RD #E BYRON CA 94514 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 216,728.00 38,149.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 216,728.00 38,149.00 5. Mobilization 17,100.00 0.00 6. Total Work Completed 233,828.00 7. Deductions 8. a.Contract Retentions -10,836.40 -116.03 b. Unsatisfactory Prog. -1,907.45 -1,907.45 c. Reduction after 95% Comp. 9. Total pay to Contractor 221,084.15 36,125.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,125.52