Dept. of Trans. PROGRESS Serial No. Contract No. 09-201-14-09 05-0E2424 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP UNSAT 05-MON-183-0.8/R1.9 Federal Project: NONE Progress payment No. 18 Payment period ending: 07-20-09 ODYSSEY LANDSCAPING COMPANY INC 800 W EIGHT MILE ROAD STOCKTON CA 95209 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 131,700.74 2,031.63 2.a. Extra Work 12,327.45 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 144,028.19 2,031.63 5. Mobilization 6. Total Work Completed 144,028.19 7. Deductions -600.00 -600.00 8. a.Contract Retentions -7,201.41 -101.58 b. Unsatisfactory Prog. -101.58 -101.58 c. Reduction after 95% Comp. 9. Total pay to Contractor 136,125.20 1,228.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,228.47