Dept. of Trans. PROGRESS Serial No. Contract No. 12-207-12-41 05-0E9604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 75% 05-MON-1-21.3/21.6 Federal Project: ACST-P001(542) P-P001(542) Progress payment No. 32 Payment period ending: 07-20-12 GOLDEN STATE BRIDGE INC 901 HOWE ROAD MARTINEZ CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,942,163.63 1,550,400.00 2.a. Extra Work 362,231.69 19,093.20 b. Adjustment Comp. 978,448.16 0.00 3. Materials on Hand 10,343.00 -1,215,229.00 4. Earned Subject to Retention 20,293,186.48 354,264.20 5. Mobilization 2,940,000.00 0.00 6. Total Work Completed 23,222,843.48 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,233,186.48 354,264.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 354,264.20