Dept. of Trans. PROGRESS Serial No. Contract No. 13-112-10-43 05-0E9604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 86% 05-MON-1-21.3/21.6 Federal Project: ACST-P001(542) P-P001(542) Progress payment No. 41 Payment period ending: 04-20-13 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT, SUITE D BENICIA, CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,597,167.98 986,292.40 2.a. Extra Work 734,556.19 16,297.02 b. Adjustment Comp. 1,244,310.87 0.00 3. Materials on Hand 9,714.00 -57,811.76 4. Earned Subject to Retention 25,585,749.04 944,777.66 5. Mobilization 2,940,000.00 0.00 6. Total Work Completed 28,516,035.04 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 28,524,749.04 943,777.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 943,777.66