Dept. of Trans. PROGRESS Serial No. Contract No. 02-233-14-54 05-0F0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SLO-5719 Federal Project: NONE Progress payment No. 04 Payment period ending: 08-20-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 229,095.73 83,285.65 2.a. Extra Work 288.52 288.52 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 229,384.25 83,574.17 5. Mobilization 6. Total Work Completed 229,384.25 7. Deductions -8,328.56 -8,328.56 8. a.Contract Retentions -11,469.21 -4,178.71 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 209,586.48 71,066.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 71,066.90