Dept. of Trans. PROGRESS Serial No. Contract No. 09-166-13-13 05-0F5704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 12% 05-SB-192-2.4/3.1 Federal Project: 05-SB-192-0.0/ .0 ACST-S192(3) PH-S192(3) Progress payment No. 04 Payment period ending: 06-20-09 R BURKE CORPORATION P O BOX 957 SAN LUIS OBISPO CA 934060957 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 595,323.50 413,073.00 2.a. Extra Work 4,178.38 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 599,501.88 413,073.00 5. Mobilization 61,750.00 13,000.00 6. Total Work Completed 661,251.88 7. Deductions -103,268.35 -103,268.35 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 557,983.53 322,804.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 322,804.65