Dept. of Trans. PROGRESS Serial No. Contract No. 18-233-09-20 05-0F7004 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 54% Location: Federal Project: 05-MON-68-R17.4/R18.0 NHP-P068(24) Progress payment No. 027 Payment period ending: 08-20-18 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,981,658.73 329,284.90 2. a. Extra Work 170,357.69 325.00 b. Adustment Comp. 201,946.80 0.00 3. Materials on Hand 4. Earned Subject to Retention 14,353,963.22 329,609.90 5. Mobilization 1,793,000.00 0.00 6. Total Work Completed 16,146,963.22 7. Deductions -468,665.25 -98,785.47 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,678,297.97 230,824.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 230,824.43