Dept. of Trans. PROGRESS Serial No. Contract No. 19-081-14-55 05-0F7004 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 64% Location: Federal Project: 05-MON-68-R17.4/R18.0 NHP-P068(24) Progress payment No. 034 Payment period ending: 03-20-19 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,632,565.03 144,974.40 2. a. Extra Work 201,358.45 7,771.71 b. Adustment Comp. 260,371.61 -23,541.79 3. Materials on Hand 4. Earned Subject to Retention 16,094,295.09 129,204.32 5. Mobilization 1,793,000.00 0.00 6. Total Work Completed 17,887,295.09 7. Deductions -979,390.07 -55,492.32 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,907,905.02 73,712.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 73,712.00