Dept. of Trans. PROGRESS Serial No. Contract No. 23-142-12-43 05-0F9704 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 100% Location: Federal Project: 05-MON-101-62.2/62.9 ANCH-Q101(401) Progress payment No. 012 Payment period ending: 05-20-23 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,837,280.43 699,808.50 2. a. Extra Work 286,298.58 286,298.58 b. Adustment Comp. -5,405.00 -5,405.00 3. Materials on Hand 0.00 -1,108.00 4. Earned Subject to Retention 3,118,174.01 979,594.08 5. Mobilization 292,000.00 0.00 6. Total Work Completed 3,410,174.01 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,410,174.01 979,594.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 979,594.08