Dept. of Trans. PROGRESS Serial No. Contract No. 10-327-10-05 05-0G0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 27% 33% 05-SLO-101-35.7/46.3 Federal Project: SARR-Q101(159) A-Q101(159) Progress payment No. 08 Payment period ending: 11-20-10 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,289,654.38 1,211,167.62 2.a. Extra Work 428,164.98 147,419.32 b. Adjustment Comp. -3,814.85 0.00 3. Materials on Hand 39,314.35 0.00 4. Earned Subject to Retention 6,753,318.86 1,358,586.94 5. Mobilization 608,000.00 0.00 6. Total Work Completed 7,322,004.51 7. Deductions -11,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,350,318.86 1,348,586.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,348,586.94