Dept. of Trans. PROGRESS Serial No. Contract No. 10-355-11-01 05-0G0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 35% 05-SLO-101-35.7/46.3 Federal Project: SARR-Q101(159) A-Q101(159) Progress payment No. 09 Payment period ending: 12-20-10 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,489,496.02 1,199,841.64 2.a. Extra Work 435,603.14 7,438.16 b. Adjustment Comp. -3,814.85 0.00 3. Materials on Hand 176,607.79 137,293.44 4. Earned Subject to Retention 8,097,892.10 1,344,573.24 5. Mobilization 608,000.00 0.00 6. Total Work Completed 8,529,284.31 7. Deductions -12,500.00 -1,500.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,693,392.10 1,343,073.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,343,073.24