Dept. of Trans. PROGRESS Serial No. Contract No. 12-142-09-32 05-0G0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 83% 05-SLO-101-35.7/46.3 Federal Project: SARR-Q101(159) A-Q101(159) Progress payment No. 26 Payment period ending: 05-20-12 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,309,966.27 175,721.70 2.a. Extra Work 2,727,408.36 197,463.07 b. Adjustment Comp. 958,212.09 9,088.36 3. Materials on Hand 195,118.28 0.00 4. Earned Subject to Retention 25,190,705.00 382,273.13 5. Mobilization 640,000.00 0.00 6. Total Work Completed 25,635,586.72 7. Deductions -50,000.00 1,500.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,780,705.00 383,773.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 383,773.13