Dept. of Trans. PROGRESS Serial No. Contract No. 12-297-07-48 05-0G0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 100% 05-SLO-101-35.7/46.3 Federal Project: SARR-Q101(159) A-Q101(159) Progress payment No. 31 Payment period ending: 10-20-12 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,581,252.18 247,254.12 2.a. Extra Work 4,278,767.55 411,785.40 b. Adjustment Comp. 1,024,520.23 -2,339.71 3. Materials on Hand 164,493.35 -3,964.03 4. Earned Subject to Retention 28,049,033.31 652,735.78 5. Mobilization 640,000.00 0.00 6. Total Work Completed 28,524,539.96 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 28,689,033.31 652,735.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 652,735.78