Dept. of Trans. PROGRESS Serial No. Contract No. 12-333-10-29 05-0G0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 100% 05-SLO-101-35.7/46.3 Federal Project: SARR-Q101(159) A-Q101(159) Progress payment No. 32 Payment period ending: 11-20-12 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,904,811.22 323,559.04 2.a. Extra Work 4,623,272.34 344,504.79 b. Adjustment Comp. 1,019,998.27 -4,521.96 3. Materials on Hand 164,493.35 0.00 4. Earned Subject to Retention 28,712,575.18 663,541.87 5. Mobilization 640,000.00 0.00 6. Total Work Completed 29,188,081.83 7. Deductions -166,613.25 -166,613.25 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 29,185,961.93 496,928.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 496,928.62