Dept. of Trans. PROGRESS Serial No. Contract No. 13-023-10-01 05-0G0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 100% 05-SLO-101-35.7/46.3 Federal Project: SARR-Q101(159) A-Q101(159) Progress payment No. 34 Payment period ending: 01-20-13 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,929,787.08 -6,973.90 2.a. Extra Work 5,297,918.69 503,971.71 b. Adjustment Comp. 1,019,998.27 0.00 3. Materials on Hand 162,358.92 -2,134.43 4. Earned Subject to Retention 29,410,062.96 494,863.38 5. Mobilization 640,000.00 0.00 6. Total Work Completed 29,887,704.04 7. Deductions -478.64 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 30,049,584.32 494,863.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 494,863.38