Dept. of Trans. PROGRESS Serial No. Contract No. 13-052-10-08 05-0G0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 100% 05-SLO-101-35.7/46.3 Federal Project: SARR-Q101(159) A-Q101(159) Progress payment No. 35 Payment period ending: 02-20-13 PAPICH CONSTRUCTION COMPANY INC P O BOX 2210 PISMO BEACH CA 93448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 23,247,132.90 317,345.82 2.a. Extra Work 5,367,519.38 69,600.69 b. Adjustment Comp. 1,019,550.05 -448.22 3. Materials on Hand 145,895.41 -16,463.51 4. Earned Subject to Retention 29,780,097.74 370,034.78 5. Mobilization 640,000.00 0.00 6. Total Work Completed 30,274,202.33 7. Deductions -478.64 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 30,419,619.10 370,034.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 370,034.78