Dept. of Trans. PROGRESS Serial No. Contract No. 18-081-15-08 05-0G0404 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 46% Location: Federal Project: 05-SLO-101-63.2/R69.3 ACNH-PQ10-1(306) 05-MON-101-R0.0/R1.9 Progress payment No. 014 Payment period ending: 03-20-18 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,065,360.52 1,010,807.42 2. a. Extra Work 205,489.25 2,729.08 b. Adustment Comp. 3. Materials on Hand 0.00 -31,545.43 4. Earned Subject to Retention 11,270,849.77 981,991.07 5. Mobilization 2,364,577.55 0.00 6. Total Work Completed 13,635,427.32 7. Deductions -65,272.77 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,570,154.55 981,991.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 981,991.07