Dept. of Trans. PROGRESS Serial No. Contract No. 18-141-09-46 05-0G0404 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 53% Location: Federal Project: 05-SLO-101-63.2/R69.3 ACNH-PQ10-1(306) 05-MON-101-R0.0/R1.9 Progress payment No. 016 Payment period ending: 05-20-18 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,150,099.68 2,652,169.63 2. a. Extra Work 275,965.05 40,517.57 b. Adustment Comp. 3. Materials on Hand 468,460.00 468,460.00 4. Earned Subject to Retention 15,894,524.73 3,161,147.20 5. Mobilization 2,364,577.55 0.00 6. Total Work Completed 17,790,642.28 7. Deductions -75,272.77 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,183,829.51 3,151,147.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,151,147.20