Dept. of Trans. PROGRESS Serial No. Contract No. 18-295-20-12 05-0G0404 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 73% Location: Federal Project: 05-SLO-101-63.2/R69.3 ACNH-PQ10-1(306) 05-MON-101-R0.0/R1.9 Progress payment No. 021 Payment period ending: 10-20-18 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,707,191.67 1,372,272.94 2. a. Extra Work 535,772.96 29,378.20 b. Adustment Comp. 57,095.65 53,595.65 3. Materials on Hand 401,830.00 -33,178.00 4. Earned Subject to Retention 22,701,890.28 1,422,068.79 5. Mobilization 2,364,577.55 0.00 6. Total Work Completed 24,664,637.83 7. Deductions -63,272.77 16,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 25,003,195.06 1,438,068.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,438,068.79