Dept. of Trans. PROGRESS Serial No. Contract No. 15-238-13-34 05-0G0704 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 39% Location: Federal Project: 05-SB-101-22.3/23.0 NH-Q101(233) Progress payment No. 020 Payment period ending: 08-20-15 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,264,932.35 757,510.60 2. a. Extra Work 403,140.42 19,302.61 b. Adustment Comp. 284,065.17 -5,547.18 3. Materials on Hand 51,700.00 0.00 4. Earned Subject to Retention 10,003,837.94 771,266.03 5. Mobilization 1,224,250.40 0.00 6. Total Work Completed 11,176,388.34 7. Deductions -69,182.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,158,906.34 770,266.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 770,266.03