Dept. of Trans. PROGRESS Serial No. Contract No. 16-054-14-54 05-0G0704 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 54% Location: Federal Project: 05-SB-101-22.3/23.0 NH-Q101(233) Progress payment No. 026 Payment period ending: 02-20-16 FLATIRON WEST, INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,206,529.80 362,862.65 2. a. Extra Work 674,245.28 59,393.94 b. Adustment Comp. 368,405.17 0.00 3. Materials on Hand 4. Earned Subject to Retention 14,249,180.25 422,256.59 5. Mobilization 1,224,250.40 0.00 6. Total Work Completed 15,473,430.65 7. Deductions -192,299.80 -25,117.80 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,281,130.85 397,138.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 397,138.79