Dept. of Trans. PROGRESS Serial No. Contract No. 13-295-10-13 05-0G1604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 91% 05-SB-166-0.9/2.4 Federal Project: 05-SB-166-3.8/4.8 STP-P166(31) Progress payment No. 05 Payment period ending: 10-20-13 RAMINHA CONSTRUCTION INC 6805 SYCAMORE ROAD ATASCADERO CA 93422 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,237,071.28 243,817.26 2.a. Extra Work 79,337.14 23,723.66 b. Adjustment Comp. 3. Materials on Hand 0.00 -7,881.90 4. Earned Subject to Retention 1,316,408.42 259,659.02 5. Mobilization 105,500.00 0.00 6. Total Work Completed 1,421,908.42 7. Deductions -11,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,410,908.42 249,659.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 249,659.02