Dept. of Trans. PROGRESS Serial No. Contract No. 08-268-16-08 05-0G8934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 93% 05-MON-101-R14.6/R19.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-20-08 SIERRA EQUIPMENT RENTAL INC 8176 ROAD 44 GLENN CA 95943 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 573,441.36 429,739.46 2.a. Extra Work b. Adjustment Comp. -1,970.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 571,471.36 429,739.46 5. Mobilization 93,500.00 23,375.00 6. Total Work Completed 664,971.36 7. Deductions -10,622.00 -10,515.50 8. a.Contract Retentions -28,573.57 -14,400.38 b. Unsatisfactory Prog. -21,486.97 -21,486.97 c. Reduction after 95% Comp. 9. Total pay to Contractor 604,288.82 406,711.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 406,711.61