Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-295-14-22 05-0G8934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-MON-101-R14.6/R19.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 10-17-08 SIERRA EQUIPMENT RENTAL INC 8176 ROAD 44 GLENN CA 95943 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 876,998.11 303,556.75 2.a. Extra Work b. Adjustment Comp. -1,970.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 875,028.11 303,556.75 5. Mobilization 93,500.00 0.00 6. Total Work Completed 968,528.11 7. Deductions -45,480.00 -34,858.00 8. a.Contract Retentions -28,573.57 0.00 b. Unsatisfactory Prog. 0.00 21,486.97 c. Reduction after 95% Comp. 28,573.57 28,573.57 9. Total pay to Contractor 923,048.11 318,759.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 318,759.29