Dept. of Trans. PROGRESS Serial No. Contract No. 05-206-08-01 05-0H0904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 11% 05-SB-101-47.9/R50.8 Federal Project: ACST-Q101(92) PHG-Q101(92) Progress payment No. 02 Payment period ending: 07-20-05 A J DIANI CONSTRUCTION CO INC P O BOX 636 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 206,371.48 120,168.15 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 206,371.48 120,168.15 5. Mobilization 88,000.00 88,000.00 6. Total Work Completed 294,371.48 7. Deductions -79,592.87 -52,042.04 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 214,778.61 156,126.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 156,126.11