Dept. of Trans. PROGRESS Serial No. Contract No. 09-266-11-10 05-0H1904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 98% 05-SLO-101-R24.0/32.3 Federal Project: ACNH-Q101(142) Progress payment No. 13 Payment period ending: 09-20-09 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,841,447.45 2,943,103.87 2.a. Extra Work 825,442.87 221,711.50 b. Adjustment Comp. -327,391.01 -571,841.62 3. Materials on Hand 4. Earned Subject to Retention 13,339,499.31 2,592,973.75 5. Mobilization 340,000.00 0.00 6. Total Work Completed 13,679,499.31 7. Deductions -3,980.00 -40.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,675,519.31 2,592,933.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,592,933.75