Dept. of Trans. PROGRESS Serial No. Contract No. 09-295-10-28 05-0H1904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 94% 05-SLO-101-R24.0/32.3 Federal Project: ACNH-Q101(142) Progress payment No. 14 Payment period ending: 10-20-09 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,917,043.88 1,075,596.43 2.a. Extra Work 933,596.21 108,153.34 b. Adjustment Comp. -565,057.96 -237,666.95 3. Materials on Hand 4. Earned Subject to Retention 14,285,582.13 946,082.82 5. Mobilization 340,000.00 0.00 6. Total Work Completed 14,625,582.13 7. Deductions -3,980.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,621,602.13 946,082.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 946,082.82