Dept. of Trans. PROGRESS Serial No. Contract No. 09-356-09-12 05-0H1904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 85% 05-SLO-101-R24.0/32.3 Federal Project: ACNH-Q101(142) Progress payment No. 17 Payment period ending: 12-20-09 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,831,666.86 161,971.44 2.a. Extra Work 1,276,062.43 100,946.10 b. Adjustment Comp. -580,401.96 -15,344.00 3. Materials on Hand 4. Earned Subject to Retention 15,527,327.33 247,573.54 5. Mobilization 340,000.00 0.00 6. Total Work Completed 15,867,327.33 7. Deductions -3,990.00 -10.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,863,337.33 247,563.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 247,563.54