Dept. of Trans. PROGRESS Serial No. Contract No. 10-167-14-54 05-0H1904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SLO-101-R24.0/32.3 Federal Project: ACNH-Q101(142) Progress payment No. 23 Payment period ending: 06-20-10 CALPORTLAND CONSTRUCTION P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,033,904.68 4,336.26 2.a. Extra Work 1,649,908.71 20,076.63 b. Adjustment Comp. -167,653.70 0.00 3. Materials on Hand 4. Earned Subject to Retention 16,516,159.69 24,412.89 5. Mobilization 340,000.00 0.00 6. Total Work Completed 16,856,159.69 7. Deductions -9,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,847,159.69 19,412.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,412.89