Dept. of Trans. PROGRESS Serial No. Contract No. 12-235-10-15 05-0H4304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 34% 05-SCR-129-3.5/ .0 Federal Project: ACST-P129(15) P-P129(15) Progress payment No. 02 Payment period ending: 08-20-12 SPECAILTY CONSTRUCTION INC 645 CLARION CT SAN LUIS OBISPO CA 93401 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 139,121.72 45,846.40 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 139,121.72 45,846.40 5. Mobilization 82,650.00 17,400.00 6. Total Work Completed 221,771.72 7. Deductions -29,626.22 -6,237.10 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 192,145.50 57,009.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,009.30