Dept. of Trans. PROGRESS Serial No. Contract No. 04-295-08-07 05-0J0504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 44% 05-SLO-101-37.3/41.3 Federal Project: ACST-Q101(78) PHG-Q101(78) Progress payment No. 02 Payment period ending: 10-20-04 SOUZA CONSTRUCTION INC P O BOX 3810 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 372,011.75 336,678.00 2.a. Extra Work 361.81 361.81 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 372,373.56 337,039.81 5. Mobilization 19,095.00 19,095.00 6. Total Work Completed 391,468.56 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 391,468.56 356,134.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 356,134.81