Dept. of Trans. PROGRESS Serial No. Contract No. 05-025-07-32 05-0J0504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 66% 05-SLO-101-37.3/41.3 Federal Project: ACST-Q101(78) PHG-Q101(78) Progress payment No. 05 Payment period ending: 01-20-05 SOUZA CONSTRUCTION INC P O BOX 3810 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 665,257.14 75,832.06 2.a. Extra Work 11,519.94 7,356.86 b. Adjustment Comp. 524.77 0.00 3. Materials on Hand 278,605.44 -40,394.56 4. Earned Subject to Retention 955,907.29 42,794.36 5. Mobilization 20,100.00 0.00 6. Total Work Completed 697,401.85 7. Deductions -19,258.02 -18,958.02 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 956,749.27 23,836.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,836.34